Project name | : West End Power Plant (WEPP) 12 Generators Installation in US Embassy |
Client | : PAE / US Department of State |
Location | : US Embassy compound, Baghdad |
Value | : $141,339.00 |
Date of Award | : February 2017 |
Date completed | : May 2017 |
Disconnect/Remove 12 Generators
Disconnect old 12 Generators sets. This includes disconnecting all electrical, mechanical and plumbing connections, control wiring, cable terminations, electrically-controlled louvers, canvas and noise dampers. Taking the generators sets out of the WEPP building and ship the units to Camp Olympia.
Install new Generators
Install 12 New Caterpillar Type D3512 TA, 1275 KVA Prime Generators sets one at a time in the vacated generator set located inside the WEPP. This includes, modifying the existing generator set location to support installation of the new generator sets (The existing exhaust stack), reinstalling all electrical, mechanical and plumbing connections, control wiring, cable terminations, electrically-controlled louvers, canvas and noise dampers.
Performance Testing
Load and performance test new generator sets installed in the WEPP to ensure new generators are fully-mission-capable.