Head Quarter Building for the Future Iraqi Petroleum Research & Development Centre

 

Head Quarter Building for the Future Iraqi Petroleum Research & Development Centre
Contract Value : I.D 11,993,594,840.00
Contract no. : 5 / 2013
Date of award : 7th of Oct. 2013
Date of contract sign : 27th Nov. 2012
Date of start : 30th of Oct. 201
Completion date :
Client : Iraqi Ministry of Oil
Location : Baghdad Iraq

Project Description  :

Iraqi Oil Ministry has awarded Fromewill ltd the construction of 10 Story (Ground Floor plus 9 Floors) Head Quarter Building for the future Iraqi Petroleum Research & Development Centre.

The work includes:

Civil Work:

102 pcs.                20m length x 80 cm Reinforced Concrete Piles.

585 m3                  Raft foundation Excavation & Backfilling.

7100 m3               Reinforced Concrete for Foundations and Skeleton Structure.

800 m3                  Non-Reinforced Concrete.

6100 m2               External and Internal Brick Works.

40 lm                     Internal Partitioning Aluminium Double Glazing.

1700 m2               Aluminium Double-Glazed Windows.

550 m2                  Wooden Doors.

3600 m2               Suspended Ceiling.

14500 m2             Internal Plastering, walls and ceilings.

11600 m2             Internal Painting.

1200 m2               Ceramic Works for walls and floors.

8250 m2               Marble Works for walls and floors.

25 m2                    Glass External Cladding

600 m2                  Elevators Internal and External Glass Cladding.

5100 m2               Alucobond External Cladding.

300 m2                  Stone External Cladding.

400 m2                  Granite External Cladding.

2600 m2               External Plastering

2600 m2               External Painting.

900 m2                  Roofing

 

Sanitary Works:

1200 lm Sewers PVC piping complete with all needed accessories.

13 pcs.                  External Concrete Manholes.

1 pc.                       9.4 x 3.6 x 3.65 m Concrete Septic tank.

260 lm                   PVC Rain Water Piping complete with all needed accessories.

1550 lm Cold and Hot Water piping complete with all accessories.

20 pcs.                  Hot water Boilers.

LS                            Sanitary Fixtures.

1 No.                     Fire Fitting System complete with a Pumping Station, and all needed accessories.

1 No.                     Water System complete with a Pumping Station and all needed accessories.

 

Mechanical Works:

10 pcs.                  DX Coil Air-Conditioning Split Units with External and Internal Units having cooling capacities from 38 to 50 Tons complete with Electrical Heaters.

1200 lm                 Galvanized Supply Air Duct complete with, silencers, grills, diffusers and all needed accessories.

43 pcs.                  Exhaust fans.

 

Electrical Works:

1 No.                     500 kVA Power Generator complete with one day and one-week fuel

storage tanks.

1 No.                     1000 kVA Power Generator complete with one day and one-week fuel storage tanks.

1 No.                     1600 kV Kiosk Type Transformer.

14 No.                   Distribution Boards.

1000 lm LV Cabling complete with all needed accessories.

4 No.                     Elevators, Panoramic Type. Each 750kg x 10 Persons, 10 Stops.

LS                            Lighting System.

LS                            Tel. System.

LS                            Fire Alarm System.

LS                            Internet System.

LS                            Satellite System.

LS                            Earthling and Lightning System.

 

 